Chevron Thailandplatform removal
>35,000t
Total weight
36
Platforms
250+
Deliverables
OFFSHORE DECOMMISSIONING
36 Wellhead Platform Removals and 13 Spool Installations, Gulf of Thailand
Engineering for Fourcask across all 36 platform removals: lifting and rigging, transport and seafastening, and mooring.
- Client
- Fourcask, Mermaid / Chevron E&P Thailand
- Year
- 2025
- Country
- Thailand
- Sector
- Oil, Gas and Marine
- Service
- Offshore decommissioning
- Status
- Executed
Scope
- 01Mooring analysis and anchor patterns
- 02Lifting and rigging: jacket, topside, spool, line pipe
- 03Spreader bar design, padeye modification
- 04Transportation and seafastening
- 05Weight control, jacket on-bottom stability


Platform Decommissioning, Offshore Thailand
Platform and pipeline removal and transport to the onshore base, for Fourcask. All offshore Thailand.

~700 t
PMWA, 2025

~1,039 t
BAWD

~887 t
BAWE

>1,300 t
ERWZA

~1334 t
SAWV, 2025

~1,042 t
PWMD

~1,083 t
PMWI

~1,050 t
ERPE Platform and Bridge

>1,100 t
JKWB Jacket

~1,500 t
SGWD

~897 t
JKWE

>1,500 t
STWB

>1,600 t
PLWK