Skip to main content
Crane barge removing an offshore platform in the Gulf of Thailand

Chevron Thailandplatform removal

  • >35,000t

    Total weight

  • 36

    Platforms

  • 250+

    Deliverables

OFFSHORE DECOMMISSIONING

36 Wellhead Platform Removals and 13 Spool Installations, Gulf of Thailand

Engineering for Fourcask across all 36 platform removals: lifting and rigging, transport and seafastening, and mooring.

Client
Fourcask, Mermaid / Chevron E&P Thailand
Year
2025
Country
Thailand
Sector
Oil, Gas and Marine
Service
Offshore decommissioning
Status
Executed

Scope

  1. 01Mooring analysis and anchor patterns
  2. 02Lifting and rigging: jacket, topside, spool, line pipe
  3. 03Spreader bar design, padeye modification
  4. 04Transportation and seafastening
  5. 05Weight control, jacket on-bottom stability
Platform topside lifted by a crane vesselLine pipe lifted over the sea

Platform and pipeline removal and transport to the onshore base, for Fourcask. All offshore Thailand.

  • Platform removal photo 1

    ~700 t

    PMWA, 2025

  • Platform removal photo 2

    ~1,039 t

    BAWD

  • Platform removal photo 3

    ~887 t

    BAWE

  • Platform removal photo 4

    >1,300 t

    ERWZA

  • Platform removal photo 5

    ~1334 t

    SAWV, 2025

  • Platform removal photo 6

    ~1,042 t

    PWMD

  • Platform removal photo 7

    ~1,083 t

    PMWI

  • Platform removal photo 8

    ~1,050 t

    ERPE Platform and Bridge

  • Platform removal photo 9

    >1,100 t

    JKWB Jacket

  • Platform removal photo 10

    ~1,500 t

    SGWD

  • Platform removal photo 11

    ~897 t

    JKWE

  • Platform removal photo 12

    >1,500 t

    STWB

  • Platform removal photo 13

    >1,600 t

    PLWK